MDOT SHA MAJOR PLANNED MAJOR WEEKEND LANE CLOSURE UPDATE (11/30/18 – 12/03/18)

All Work is Weather Dependent
 
Real-Time travel conditions and live traffic cameras are available - md511.maryland.gov.

Major Weekend Lane Closures

Anne Arundel County

• Northbound I-895 Bridge over the Patapsco Flats (Between MD 295 and the I-97/MD spur) – Bridge rehabilitation – (MDTA project) 24/7 right lane closure until summer 2019.

Baltimore County

• Inner loop of I-695 (Baltimore Beltway) ramp to southbound I-83 (Jones Falls Expressway) - Routine bridge inspection – Ramp closure and detour (using Falls Road toward Joppa Road – U-turn and back to SB I-83) Sunday between 4 a.m. and 7 a.m. new

Montgomery County

• Northbound I-270 between Democracy Boulevard and Montrose Road - Resurfacing - Single and double lane closures Sunday nights through Friday mornings 8 p.m. and 5 a.m.

• US 29 (Colesville Road) between I-495 (Capital Beltway) and MD 97 (Georgia Avenue) - WSSC water line replacement project - Single and double lane closures Mondays through Fridays between 9:30 a.m. to 3:30 p.m. and Sundays through Friday mornings between 9 p.m. and 5 a.m. Single lane closures Saturday between 9 a.m. and 5 p.m.

Queen Anne’s County

• MD 213 (Church Hill Road) between Schrader Road and the Chester River Bridge – Pavement repair (patching) – Single lane closure with flagging operation Friday and Saturday between 7 p.m. and 6 a.m. each night. new
 
Talbot County

• MD 322 (Easton Parkway) and MD 33 (Saint Michaels Road) in the Town of Easton – Pavement repair (patching) – Single lane closure with flagging operation beginning Sunday and continuing until completion between 7 p.m. and 6 a.m. each night. new

Long-Term Closures
 
Baltimore City

HIGH-IMPACT - (MDTA Project) - I-895 (Baltimore Harbor Tunnel Throughway) between the tunnels and Boston Street/O’Donnell Street (exit 11) and the Holabird Avenue exit. – Bridge rehabilitation project – Northbound I-895 to close on November 27 and two-way traffic using southbound I-895. Use I-95 (Fort McHenry Tunnel) or I-695 (Francis Scott Key Bridge) as alternate routes. Project to last until 2021.

Baltimore County

HIGH-IMPACT - Outer loop of I-695 (Baltimore Beltway) ramp to Edmonson Avenue – Ramp closure for widening project – Motorists will be guided to I-695/MD 144 (Frederick Road) interchange and back to the inner loop I-695 to Edmonson Avenue Deerco Road to the I-83/Timonium Road interchange. In approximately three weeks, the Edmonson Avenue ramp to the outer loop I-695 will also close. Local detours.

• Eastbound Padonia Road ramp to northbound I-83 – Ramp closure for bridge replacement project – Motorists will be guided to Deerco Road to the I-83/Timonium Road interchange.

Frederick County
 
• Eastbound US 40 Alternate (Old National Pike) between Fern Lane and Ridge Road – Roadside slope repair – Right truck “climbing” lane and shoulder closed.

Prince George’s County

• US 301 (Crain Highway) between Frank Tippett Road and Trumps Hill Road - Gas pipeline construction and installation (Washington Gas project) – Single right lane closure through spring 2019.

Somerset/Worcester County line

• US 13 (Ocean Highway) northbound over Pocomoke River at the Worcester/Somerset county line – Bridge work – Northbound US 13 bridge over Pocomoke River has been reduced to one 12-foot lane for bridge work through the late-fall.

Wicomico County

• MD 349 (Nanticoke Road) Rockawalkin Road – Washout/major road repair – MD 349 is closed and detoured until early 2019. 

MAJOR Closures for Next Week
 
Anne Arundel County

• MD 181 (6th Street) Bridge over Spa Creek – Routine drawbridge maintenance – Occasional brief test openings on Wednesday, December 5 between8:30 a.m. and 2:30 p.m. new

Baltimore County

• Southbound I-83 (Baltimore-Harrisburg Expressway) at Padonia Road – Lane shifts for bridge replacement project – On Monday, December 3, traffic will be shifted on southbound I-83 and will include single and double closures. All lanes will open by 5 a.m. Tuesday. This work is temperature permitting. new

Carroll County

• MD 86 (Lineboro Road) between MD 30 (Hanover Pike) and the Pennsylvania line – Pavement repair – Single lane closures guided by flaggers Monday through Friday between 8 a.m. and 4 p.m. Complete early-December.

Frederick County

• MD 355 (Urbana Pike) Bridge over the Monocacy River – Bridge approach paving – Single lane closures guided by flaggers beginning Monday, December 3 between 8 a.m. and 4 p.m. new date

• Park Mills Road Bridge over I-270 – Bridge approach paving – Single lane closures guided by flaggers beginning Monday, December 3 between 8 a.m. and 4 p.m. new date

Montgomery County

• Northbound I-270 at MD 109 (Old Hundred Road) – Paving/line striping – On northbound I-270 - Single lane closures Mondays through Fridays between 9 a.m. and 11 a.m.

• MD 97 (Georgia Avenue) between north of Goldmine Road and south of Holiday Drive - Bypass construction – Single lane closures Mondays through Fridays between 8 a.m. and 3 p.m.

Washington County

• I-81 between the Potomac River Bridge (West Virginia line) and MD 68/MD 63 (Lappans Road) – Highway widening project – Left lane closures Sunday nights through Friday mornings between 9 p.m. and 5 a.m. There may be occasional, brief total closures to move equipment and material into place between 2 a.m. and 4 a.m.
 
Click here to visit SHA on Facebook!  Click here to follow SHA on Twitter!  Click here to follow SHA on Pinterest!  Click here to view SHA's Channel on YouTube!  Click here to view MD 511
 
Take Our Website Survey