SHA PLANNED LANE CLOSURE UPDATE (11/01/13 TO 11/07/13)

MDOT SHA Logo

MDOT SHA Logo

(All work is weather permitting.)

Anne Arundel County

• Southbound I-97 between MD 100 and MD 3 Business (Crain Highway/New Cut Road)Concrete patching –single and double lane closures beginning at 10 p.m. Saturday through 5 a.m. Monday.  

Baltimore County

• MD 26 (Liberty Road) between the Baltimore City line and I-695 (Baltimore Beltway)Resurfacing - single lane closures Mondays through Fridays between 9 a.m. and 3 p.m. as well as 7 p.m. to 5 a.m. Sundays through Thursdays. 
 
• Northbound I-95 at the Baltimore/Howard County line (bridge over the Patapsco River) Patching – Double lane closures beginning at 10 p.m. Sunday to 5 a.m. Monday.
 
 MD 157 (Merritt Boulevard) between Wise Avenue and Peninsula ExpresswayPatching/resurfacing – Single lane closures Mondays through Fridays from 9 a.m. until 3 p.m.
 
• Northbound I-795 Bridge over Gwynns Falls Routine bridge inspection –Single right lane closure on northbound I-795 from 6 a.m. to 10 a.m. Saturday.
 
• Inner loop I-695 Bridge over MTA Metro tracks (Pikesville)Routine bridge inspection –Single right lane closure on the inner loop I-695 from 5:30 a.m. to 10:30 a.m. Sunday.
 
• Middletown Road Bridge over I-83 (Baltimore-Harrisburg Expressway) - Bridge rehabilitation project - daily single lane closures possible on northbound and southbound I-83 Mondays through Fridays from 9 a.m. to 3 p.m.

Cecil County

• US 40 (Pulaski Highway) between Big Elk Creek Bridge and the Delaware State Line Resurfacing and storm water improvements – single lane closures Sundays through Thursdays from 9 p.m. until 5 a.m.

Harford County

• Loflin Road at MD 7 (Old Philadelphia Road) - Water line relocation – A temporary road closure is underway. Motorists are being detoured to westbound US 40 (Pulaski Highway). 
 
Montgomery County
 
• Northbound I-270 Bridge over MD 117 (West Diamond Avenue)Pavement repair (bridge joints) – Motorists should expect single lane closures on northbound I-270 beginning Sunday at 10 p.m. until 5 a.m. Monday.
 
• Southbound MD 185 (Connecticut Avenue) between Rosemary Street and the Washington D.C line Concrete bus pad installation – Closing two right lanes from 9 p.m. Friday through 5 a.m. Monday.  Click here for more project information.
 
• MD 198 (Sandy Spring Road) Bridge over I-95 Routine bridge inspection –Alternating double lane closures on southbound I-95 from 5 a.m. to 11 a.m. Sunday.
 
• MD 650 (New Hampshire Avenue) at Sligo Creek Parkway- Bridge deck rehabilitation – possible single and double lane closures on Mondays through Fridays between 5 a.m. and 3 p.m., as well as overnight Sundays through Saturdays 7 p.m. to  5 a.m. Click here for more information.
 
• MD 97 (Georgia Avenue) between the Washington D.C. line and MD 390 (16th Street) Resurfacing –Single and double lane closures Sundays through Thursdays from 10 p.m. until 5 a.m. MD 97 (Georgia Avenue) at Cameron and Spring Streets - Concrete bus pad construction – two lanes will be blocked on northbound MD 97 from 9 p.m. Friday until 12 noon Saturday.  Expect a single lane closure until 5 a.m. Monday.
 
• MD 355 (Rockville Pike) between the Washington D.C. line to MD 191 (Bradley Boulevard)Resurfacing – single and double right lane closures possible on southbound MD 355 Sunday through Thursday from 8 p.m. to 5 a.m. Click here for more information.

Prince George’s County

• Outer Loop I-95/I-495 (Capital Beltway) between D’Arcy Road and Arena Drive Resurfacing - Alternating single and double northbound and southbound lane closures overnights, Sunday through Thursday from 9 p.m. to 5 a.m. Also expect a single right lane closure from D’Arcy Road to Arena Drive from 9 p.m. Friday through 5 a.m. Sunday. Click here for more project information.
 
• US 50 (John Hanson Highway) from the Town of Cheverly to MD 202 (Landover Road)Resurfacing – single lane closures in each direction Sundays through Thursdays, between 10 p.m. and 5 a.m.
 
• MD 201 (Kenilworth Avenue) between Good Luck Road and I-95/I-495 (Capital Beltway) - Resurfacing - alternating northbound left and right single lane and shoulder closures, overnight, Sunday through Thursday, 9 p.m. to 5 a.m. 
 
• MD 193 (Greenbelt Road) from Rhode Island Avenue to Southway utility work - alternating single and double eastbound MD 193 lane closures Sundays through Thursdays from 9 p.m. until 5 a.m.
 
• MD 197 (Laurel Bowie Road) between MD 295 (Baltimore-Washington Parkway) and Brockbridge Road Turn lane extension and resurfacing – single lane closures Mondays through Fridays from 9 a.m. until 3 p.m. Single and double lane closures Sundays through Thursday from 8 p.m. until 5 a.m. Click here for more information.

While SHA and its partners work hard to maintain safe traffic mobility in work zones, each driver needs to actively modify his or her driving style to help prevent crashes. Stay alert – look for reduced speed limits, narrow driving lanes and highway workers. Slow down and don't follow too closely. Safer Driving. Safer Work Zones. For everyone!

 

###