SHA PLANNED LANE CLOSURE UPDATE (06/13/2014 – 06/20/2014)

MDOT SHA Logo

MDOT SHA Logo

(All work is weather permitting.)
 
Anne Arundel County

• New Cut Road ramp to southbound I-97 Concrete patching – Temporary ramp closure and detour on Saturday from 7 a.m. until 7 p.m.

Carroll County

• Eastbound and westbound MD 140 (Baltimore Boulevard) between MD 91 (Gamber Road) and Sandymount RoadConcrete patching - Single lane closures from 8 p.m. Friday until 6 p.m. Sunday.

• Westbound MD 140 between Old Westminster Pike to Glen Falls Road Bridge rehabilitation – The right lane will be locked on Saturday from 6 a.m. until 2 p.m.

Frederick County

• Northbound I-270 between MD 80 (Fingerboard Road) to I-70 Resurfacing – Single lane closure beginning at 8 p.m. Sunday until 5 a.m. Monday.

• MD 17 (Myersville Road) from Eagle Bay to Cedar Street Grading – Single lane closure Saturday from 8 a.m. until 4 p.m.

• Eastbound and westbound I-70 Bridge over I-270 - Routine bridge inspection – single lane closures on southbound I-270 Sunday from 5 a.m. until 9 a.m. 

Harford County

• MD 7 (Philadelphia Road) Bridge over James Run (north of MD 136) - Bridge replacement – Road will close to all traffic starting at 9 a.m. Saturday until late summer. Motorists will be directed to US 40 for the detour route. Click here for more information.

Howard County

 Northbound and southbound I-95 at MD 216 (Scaggsville Road)BGE overhead utility work – Temporary 15 minute total closures Sunday from 5 a.m. until 9 a.m.

• Northbound I-95 between the Prince George’s County line to MD 216 (Scaggsville Road) Resurfacing – Double right lane closures from 7 p.m. Friday to 5 a.m. Saturday. Crews will then block a single lane on Sunday beginning at 8 p.m. All lanes re-open by 5 a.m. Monday.

Montgomery County

• Cedar Lane between MD 355 (Rockville Pike) and Elmhirst Parkway Intersection improvements – Cedar Lane is closed in both directions.  Click here for more information.

 US 29 (Columbia Pike) Bridge over I-495 (Capital Beltway) - Routine bridge inspection – Double lane closure on the inner loop of I-495 Saturday from 4:30 a.m. until 11:30 a.m.  On Sunday, inspectors will close two lanes on the outer loop of I-495 during the same time period.

• Inner Loop and Outer Loop of I-495 (Capital Beltway) between MD 650 (New Hampshire Avenue) and US 29 (Columbia Pike) - Bridge replacement (Demolition phase) - Single and double lane closures Sundays through Thursdays from 9 p.m. to 5 a.m. There will be intermittent 15 minute total stoppages between midnight and 4 a.m.

• MD 355 (Frederick Road) from King Farm Boulevard to Central Avenue Resurfacing - Single and double lane closures Sundays through Thursdays from 9 p.m. to 5 a.m.

• MD 124 (Quince Orchard Road) from MD 115 (Muncaster Mill Road) to Lindbergh Drive Resurfacing - Single and double lane closures Sundays through Thursdays from 9 p.m. to 5 a.m.

• MD 650 (New Hampshire Avenue) at Sligo Creek Parkway- Bridge deck rehabilitation – Single and double lane closures Monday through Friday between 5 a.m. and 3 p.m., as well as overnight Sunday through Saturday from 7 p.m. until 5 a.m.

• MD 355 (Rockville Pike/Wisconsin Avenue) from MD 191 (Bradley Lane/Bradley Boulevard) to MD 187 (Old Georgetown Road) - Traffic signal utility conduit work – Single and double lane closures from 10 p.m. Sunday until 5 a.m. Monday.

• Georgia Avenue between MD 390 (16th Street) and the Washington D.C. Line Roadway grinding and patching – Single and double lane closures from 9 p.m. Sunday until 5 a.m. Monday.

Prince George’s County

• MD 4 (Pennsylvania Avenue) from Ritchie Marlboro Road to Dower House Road Resurfacing – Double lane closures in both directions Sundays through Thursdays from 9 p.m. to 5 a.m.

• Inner Loop of I-495 (Capital Beltway) between Glenarden Parkway and US 50 (John Hanson Highway) - Median construction - Single lane closures Sundays through Thursdays from 9 p.m. to 5 a.m.

• MD 725 (Marlboro Pike) from Old Marlboro Pike to MD 202 (Largo Road) - Road resurfacing - Single and double lane closures Sundays through Thursdays from 9 p.m. to 5 a.m.

• US 1 (Baltimore Avenue) from Indian Lane to Hollywood Road - Resurfacing - Single and double lane closures Sundays through Thursdays from 9 p.m. until 5 a.m.

• Westbound MD 193 (Greenbelt Road) between Rhode Island Avenue and Southway Paving/Resurfacing – Double lane closures from 9 p.m. Sunday until 5 a.m. Monday.
 
 

 
While SHA and its partners work hard to maintain safe traffic mobility in work zones, each driver needs to actively modify their driving style to help prevent crashes. Stay alert – look for reduced speed limits, narrow driving lanes and highway workers. Slow down and don't follow too closely. Safer Driving. Safer Work Zones. For everyone!

###