MDOT SHA MAJOR PLANNED MAJOR WEEKEND LANE CLOSURE UPDATE (07/07/2017 – 07/10/2017)

MDOT SHA Logo

MDOT SHA Logo

For A listing of ALL Major MDOT SHA Projects spring through fall, click here for e-Road Ready 2017, an interactive map of major MDOT SHA projects.

Major Weekend Lane Closures

 Baltimore County

• (MDTA Project) Inner loop of I-695 (Baltimore Beltway) between US 1 (Belair Road) and I-95 – Final paving/striping associated with Express Toll Lane Project – Double lane closures on the outer loop I-695 Sundays through Friday mornings between 9 p.m. and 5 a.m.  Should be complete by early August.

• Inner loop of I-695 (Baltimore Beltway) ramp to MD 147 (Harford Road) – Ramp paving associated with beltway widening and interchange reconstruction – Ramp closure and detour Sunday between 9 p.m. and 5 a.m. Monday

• Inner loop and outer loop of I-695 (Baltimore Beltway) between MD 147 (Harford Road) and MD 41 (Perring Parkway) – Final paving/striping associated interchange reconstruction/bridge replacement project – Double lane closures on the outer loop I-695 Sundays through Fridays between 9 p.m. and 5 a.m. 
 
• Northbound I-83 between Shawan Road and MD 137 (Mt. Carmel Road) – Resurfacing – Single lane and shoulder closures Sundays through Fridays between 8 p.m. and 5 a.m.
 
Frederick County

• MD 80 (Fingerboard Road) between MD 75 (Green Valley Road) and the Montgomery County line – Resurfacing – Single lane closure guided by flaggers Sunday nights to Friday mornings between 8 p.m. and 5 a.m.
 

Montgomery County

• MD 355 (Rockville Pike) between Wilson Drive and Woodmont Avenue - Montgomery County Crossing Project clearing and curb work - Single and double left and right lane closures in each direction beginning Friday at 9 p.m. until 5 a.m. Monday.
 
• MD 189 (Falls Road) Bridge over I-270 -  Routine bridge inspection – Single lane closures Saturday between 4 a.m. and 12 noon.

• Inner Loop Capital Beltway (I-495) between MD 97 (Georgia Avenue) and MD 355 (Wisconsin Avenue) -  Resurfacing - Work complete.
 
Prince George’s County

• Westbound US 50 (John Hanson Highway) between the Anne Arundel County Line and Lottsford Vista Road - Resurfacing – Single, double and triple lane closures Fridays through Mondays between 10 p.m. and 5 a.m. and double lane closures Sundays through Thursdays between 10 p.m. and 5 a.m.

• Southbound I-95 (inner loop I-495) Bridge over Rhode Island Avenue – Bridge deck repairs – Single and double lane closures Sundays through Friday mornings between 9 p.m. and 5 a.m.

• Inner and outer loops (north and southbound I-95) of I-95/I-495 (Capital Beltway) between MD 337 (Allentown Road) and MD 4 (Pennsylvania Avenue) – Shoulder construction/Interchange work – Single and double lane closure in each direction Sundays through Fridays from 7 p.m. until to 5:00 a.m.

• MD 201 (Kenilworth Avenue) between 48th Street and Riverdale Road – Resurfacing - Single lane closures Saturday from 9 a.m. until 3 p.m.

Long-Term Closures
 
Baltimore County

• MD 147 (Harford Road) at Glen Arm Road/Mt. Vista Road – Roundabout construction –Glen Arm Road is closed and detoured. 
 
Charles County

• MD 234 (Budds Creek Road) Bridge over Gilbert Swamp Run – Bridge replacement – Single lane closure guided by a temporary traffic signal until spring 2018.  
 
Dorchester County

• Eastbound MD 16 (Church Creek Road) to close at Woods Road. Woods Road closed south of MD 16 (Church Creek Road) – Roundabout construction – local detour in effect. (Opening Wednesday, July 12 – Weather permitting.)
 
• MD 335 (Golden Hill Road) to more than one mile south of Hip Roof Road – Culvert replacement – local detour in effect.  The closure will begin on Monday Morning, June 26 until the end of July. (opened ahead of schedule)

Frederick County
 
• MD 194 (Woodsboro Pike) Bridge over Little Pipe Creek (at the Carroll County line) – Bridge replacement project –Bridge closed for 10 weeks for expedited replacement on June 17 until September 4, 2017.
 
Washington County

• MD 63 (Spielman Road) Bridge over St. James Run – Culvert replacement – Total closure and detour between June 5 and August 14 to expedite the work. 

Wicomico County
 
• Southbound US 13 ramp/bridge to the eastbound/southbound Salisbury Bypass – Bridge/ramp rehabilitation – Total closure and detour until early September to expedite the work.

A look ahead at next week

Baltimore County
 
• Inner loop and Outer loop of I-695 (Baltimore Beltway) between MD 147 (Harford Road) and MD 41 (Perring Parkway) – Paving operations/Interchange reconstruction – Double lane closures Sundays through Thursdays between 9 p.m. until 5 a.m. each morning.

• Southbound MD 129 (Park Heights Avenue) between MD 133 (Old Court Road) and Baltimore City line (BGE project) – BGE Gas line replacement project – Single lane closures Mondays through Fridays between 9 a.m. until 3 p.m.

• Southbound I-95 on the Bridge over the Patapsco River (Baltimore/Howard County line) – Bridge deck (driving surface) sealing – Single and double lane closures Sundays through Thursdays between 7 p.m. until 5 a.m.

Caroline/Queen Anne’s/Talbot counties

• MD 404 (Queen Anne Highway/Shore Highway) between US 50 (Ocean Gateway) and MD 309 (Starr Road) and MD 480 (Ridgely Road) and the Denton Bypass – Highway widening – Single lane closures with flagging operations possible between 12 noon Mondays until 12 noon Fridays.  All lanes open each evening.  
 
Cecil County

• MD 272 Bridge over the Amtrak tracks – Preliminary bridge replace work – Possible single lane closures Mondays through Fridays between 9 a.m. and 3 p.m. 
 
Frederick County

• MD 75 (Green Valley Road) Bridge over I-70 – Concrete bridge deck patching – Single lane closures Mondays through Fridays between 9 a.m. and 3 p.m. 
 
• Southbound US 15 in the Thurmont area – Asphalt patching – Single lane closures Monday only between 9 a.m. and 3 p.m. 
 
Howard County
 
• MD 94 (Woodbine Road) at A.E. Mullinix Road – Culvert rehabilitation – Single lane closures guided by a 24-hour flagging operation between July 7 until the end of July.
 
• Northbound US 29 between Seneca Drive and MD 175 – Final paving – Single lane closure Saturday and Sunday between 8 p.m. and 5 a.m.

Montgomery County

• MD 586 (Veirs Mill Road) between the Rock Creek Bridge and Ferrara Avenue and between MD 193 (University Boulevard) – Safety and paving work - Single lane closures Mondays through Fridays from 9 a.m. until 3 p.m. and double lanes permitted Sundays through Thursdays from 9 p.m. to 5 a.m.

• MD 28 (Darnestown Road) between MD 124 (Quince Orchard Road) and Argosy Road - Sidewalk construction/part of safety/resurfacing project - Single eastbound lane closures Mondays through Fridays from 10 a.m. until 4 p.m.

Prince George’s County

• US 1 Alternate (Bladensburg Road) between Eastern Avenue (Washington D.C. line) and the Anacostia River Bridge – (Resurfacing) – Single lane closures guided by flagging Mondays through Fridays between 9 a.m. and 3 p.m. and 7 p.m. until 5 a.m. Sunday nights through Friday mornings.
 

###